La Solana Town Homes, Hayward, CA

    The La Solana project consisted of 58 two, three and four bedroom town homes targeted at first time low and moderate income buyers. The project was developed by Eden Housing a Hayward based housing oriented nonprofit organization. La Solana was one of several projects created as part of the U.S. Department of Housing and Urban Development's "Housing Cost Reduction Demonstration Program." The idea behind that program was to develop and field test ideas for reducing the cost of housing production in order to achieve affordability. The methods employed included streamlining the HUD approval process, use of HUD Section 236 financing, and other techniques. Great emphasis was also placed on energy efficiency in order to reduce the continuing cost of ownership.

    The basic plans are simple and straightforward, and the finish materials are drawn from a builder's standard list of materials. However, as it turned out the pursuit of high energy efficiency resulted in construction that was very complex and costly. Each town home had both solar assisted water heating and space heating.

    The solar assisted water heating was consistent with the state of the technology at the time of construction, roughly 1981. Each unit had a regular electric water heater, a solar storage tank, roof mounted collector panels, and the necessary electronic controls and valves to make the system work. The entire system followed standard designs and was built from off the shelf components.

    The solar assisted space heating was entirely unique. Double glazed windows and patio doors, extra weather stripping, and careful sealing of the building envelope were part of the plan as well as foam insulation under the concrete slab first floor, and substantial insulation in the second floor attic space. Those things were well accepted and tested methods at the time. But, solar space heating generally involves providing a "storage mass" which is heated by the sun during daylight hours and which then gives off the stored heat during the evening and night hours when added heating is most often needed. The designers assumed, and I think correctly, that for many people an exposed concrete or tile first floor finish would not be acceptable. It was assumed that most buyers would want carpeting. But, carpeting would insulate the concrete slab from solar heating and render it useless as a "storage mass." The designers then turned to walls as a potential location for the "storage mass." By adding large quantities of sand to gypsum plaster and then applying a 2" thick layer to all of the walls separating the units sufficient mass was achieved. Unfortunately, the devil is often in the details, and the ultimate detailing of the technique proved very difficult for all of the contractors involved. However, in the end the desired result was achieved and the end product is shown in the snapshots below. These were taken at various stages of construction, through to the finished model.

You can click on the photos below for a larger version. Use your browser's "Back" button to return here. Click "Home" to return to the homepage.  HOME


The Lot(s)

The La Solana site consisted of two lots of about 2 acres each. Located along Tenneysaon Road, they were separated By Harvey Avenue. This view is the lots from across Tenneyson.

The Lot(s)

This view is from the Harvey Avenue corner of one of the lots looking toward Tenneyson.

Footings

Footings are poured and drain plumbing in place.

Preparing For The Slab Pour

The foam insulation, reinforcing steel and pipework is in place, and perimeter forms are almost ready for the slab pout.

Preparing for Footing Pour

There were a total of eight buildings on the site. Here the steel and drain lines are in place ready for footing pour.

West Side Buildings & East Foundations

The buildings on the west side of the site are well along in framing while the foundations are being completed on the east side.

Foundations

Final check on footings.

Concrete Pour

Footing pour in a light rain. An early decision to complete all street work through curb, gutter and asphalt proved important as other builders working nearby projects without completed streets were shut down for weeks by rain.

The Bone

Our B-88 Pettibone could reach material stores in the paved area and set heavy loads on the concrete slabs overreaching the muddy yards. This allowed work to proceed under almost any conditions.

Framing Starts

The framing starts on a newly completed slab.

Framing Nearly Complete

Framing is nearly complete on this building.

East Site

Foundation work undersay on the east site. Note the stacks of material ready for use.

Framing and Finish

Framing underway on the east side while finish work is being done on the west. Note that the solar water heating panels are in place on the west side building.

Interior Under Construction

Typical of the interior under construction. Wiring and plumbing are in place and insulation is underway.

Siding

The plywood was prepainted. With careful handeling in the field only minor touch up and trim painting was required.

Siding Underway

Note the stacks of drywall ready to be stocked in the buildings.

Siding

The siding, like all other steps in the process was completed in sequence, one building at a time.

Prepainted Siding

Prepainting the siding saves time and labor over paining after installation, but the key is careful handling in the field. Careless handling can damage the paint requiring extensive touch up, or complete repainting.

Underway

Clean Up Stage

This building is nearing completion. Interior painting is underway and teh exterior is cleaned up prior to construcion of the covered parking, fencing and yard storage.

West Side Nearing Completion

The parking structures, fencing and yard storage are nearly complete on the west side and the model units (right foreground) are being landscaped.

Model Units, Exterior

The model units are nearly ready for display.

Model Four Bedroom Entry

The end units were all four bedroom with fireplace.

Entry

The entry of a four bedroom end unit.

Entry Walk

Kitchen

Typical kitchen includes the full range of standard features.

Livingroom with Fireplace

Only the four bedroom units have fireplaces but all are bright and attractive.

Master Bath

Master bath features ceramic tile tubs and attractive cabinets.

Master Bedroom

To aid in even distribution of heat a duct and small fan connect the south facing and north facing bedrooms. Electronic controls monitor individual room temperature and turn the fan on to circulate

Dining Room

Kitchen / Dining Room

Dining Room / Entry